Reliability and Cost-Benefit Analyses of the Balog-Balog Multipurpose Dam Versus Balog-Balog Multiple Dam Project

Article Details

Guillermo Q. Tabios III, gtabios@upd.edu.ph, Institute of Civil Engineering and National Hydraulic Research Center, University of the Philippines at Diliman, Quezon City and National Academy of Science and Technology

Journal: DLSU Business and Economics Review
Volume 28 Issue 1 (Published: 2018-04-01)

Abstract

This study is to compare the Balog-Balog multipurpose, single dam project with the proposed Balog-Balog multiple dam system, using reliability and cost-benefit analyses, of the ability of the two reservoir systems to deliver irrigation water supply to the Balog-Balog irrigation system including hydropower generation and flood control functions through optimization-simulation model studies. On the basis of reliability to deliver irrigation water, generate hydropower, reservoir life, people displaced due to reservoir construction, flood control benefits, and economic analysis, the Balog-Balog single, high dam is a better project compared to the multiple dam system.

Keywords: multipurpose reservoir, optimization-simulation, reliability analyses, cost-benefit analyses

DOI: https://dlsu-ber.com/reliability-and-cost-benefit-analyses-of-the-balog-balog-multipurpose-dam-versus-balog-balog-multiple-dam-project/
  References:

Box, M. J., (1965)., A new method of constrained optimization and a comparison with other methods., Computer Journal, Vol. 8(, No. 1), pp. 42– 52.

NIA Consult, Inc., (2010, May)., Updating the feasibility study for the Balog-Balog Multipurpose Project, Phase II (BBMP-II), May. Place of publication: Publisher.

NIA Consult, Inc., (2011, August). Updated proposal for the Balog-balog Multipurpose Project, August. Place of publication: Publisher.

NIA Consult, Inc., (2012, June)Final report for Balog-Balog Multipurpose Project Phase II, Technical assistance for the detailed engineering design, June. Place of publication: Publisher.

Tarlac Mini Dams Project. (TMPDP, 2012).: A proposal based on JVG IRR for a multiple run mini dams irrigation and run of the river power system along Bulsa River. Location of company proposing: Proposing Company.